This thesis analyses how deviations occurring during the construction of photovoltaic systems can affect the economic performance of an EPC project and the cost of the energy produced. Starting from a real portfolio of photovoltaic projects, a quantitative model is developed to distinguish the effects on the contractor’s project margin from those on the asset’s levelized cost of energy (LCOE). The analysis considers different types of construction-site deviations, including additional works, work suspensions, delays in the start of operation, and losses in energy production. For each case, the economic, temporal, and energy-related effects are assessed both at lot level and for the overall portfolio. The results show that the impact of these deviations depends not only on their magnitude, but also on when they occur and on how the related costs are economically recognized. The thesis also introduces a parametric analysis to estimate the maximum additional cost compatible with a given reduction in the deviation. The resulting framework provides a quantitative tool for supporting the economic assessment of construction-stage variations in photovoltaic EPC projects.

La tesi analizza come le deviazioni che possono verificarsi durante la realizzazione di impianti fotovoltaici influenzino i risultati economici di una commessa EPC e il costo dell’energia prodotta. A partire da un portafoglio reale di interventi fotovoltaici, viene sviluppato un modello quantitativo che distingue gli effetti sul margine del contractor da quelli sul costo livellato dell’energia (LCOE) dell’impianto. Sono considerate diverse tipologie di deviazione di cantiere, tra cui opere aggiuntive, sospensioni dei lavori, ritardi nell’entrata in esercizio e perdite di produzione energetica. Per ciascun caso vengono valutati gli effetti economici, temporali ed energetici sia sui singoli lotti sia sull’intero portafoglio. L’analisi mostra che l’impatto delle deviazioni dipende non solo dalla loro entità, ma anche dal momento in cui si verificano e dalle modalità con cui i relativi costi vengono riconosciuti. Il lavoro introduce inoltre un’analisi parametrica che consente di stimare il costo massimo compatibile con una determinata riduzione della deviazione. Il risultato è un modello di supporto all’analisi economica delle variazioni di cantiere in progetti fotovoltaici EPC.

PROPAGAZIONE DELLE DEVIAZIONI DI CANTIERE IN UN PORTAFOGLIO FOTOVOLTAICO EPC: EFFETTI SUL MARGINE DI COMMESSA E SUL COSTO LIVELLATO DELL’ENERGIA

CASAVOLA, MICHELE
2025/2026

Abstract

This thesis analyses how deviations occurring during the construction of photovoltaic systems can affect the economic performance of an EPC project and the cost of the energy produced. Starting from a real portfolio of photovoltaic projects, a quantitative model is developed to distinguish the effects on the contractor’s project margin from those on the asset’s levelized cost of energy (LCOE). The analysis considers different types of construction-site deviations, including additional works, work suspensions, delays in the start of operation, and losses in energy production. For each case, the economic, temporal, and energy-related effects are assessed both at lot level and for the overall portfolio. The results show that the impact of these deviations depends not only on their magnitude, but also on when they occur and on how the related costs are economically recognized. The thesis also introduces a parametric analysis to estimate the maximum additional cost compatible with a given reduction in the deviation. The resulting framework provides a quantitative tool for supporting the economic assessment of construction-stage variations in photovoltaic EPC projects.
2025
PROPAGATION OF CONSTRUCTION-SITE DEVIATIONS IN AN EPC PHOTOVOLTAIC PORTFOLIO: EFFECTS ON PROJECT MARGINS AND THE LEVELIZED COST OF ENERGY
La tesi analizza come le deviazioni che possono verificarsi durante la realizzazione di impianti fotovoltaici influenzino i risultati economici di una commessa EPC e il costo dell’energia prodotta. A partire da un portafoglio reale di interventi fotovoltaici, viene sviluppato un modello quantitativo che distingue gli effetti sul margine del contractor da quelli sul costo livellato dell’energia (LCOE) dell’impianto. Sono considerate diverse tipologie di deviazione di cantiere, tra cui opere aggiuntive, sospensioni dei lavori, ritardi nell’entrata in esercizio e perdite di produzione energetica. Per ciascun caso vengono valutati gli effetti economici, temporali ed energetici sia sui singoli lotti sia sull’intero portafoglio. L’analisi mostra che l’impatto delle deviazioni dipende non solo dalla loro entità, ma anche dal momento in cui si verificano e dalle modalità con cui i relativi costi vengono riconosciuti. Il lavoro introduce inoltre un’analisi parametrica che consente di stimare il costo massimo compatibile con una determinata riduzione della deviazione. Il risultato è un modello di supporto all’analisi economica delle variazioni di cantiere in progetti fotovoltaici EPC.
Fonti Rinnovabili
LCOE
Contratti EPC
Deviazioni cantiere
File in questo prodotto:
File Dimensione Formato  
Tesi_POLIS_Casavola_ottimizzata.pdf

non disponibili

Descrizione: Contiene il documento finale della tesi , in quanto eccessivamente pesante ho necessariamente dovuto ottimizzare l'artefatto riducendo la qualità grafica delle figure contenute
Dimensione 3.37 MB
Formato Adobe PDF
3.37 MB Adobe PDF

I documenti in UNITESI sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14253/110657